How to tell an LNG tank under construction from a finished one in satellite imagery

A finished LNG storage tank and one that's eight months from mechanical completion can look almost identical from directly overhead at certain resolutions. Both are big concrete cylinders with a round footprint and a dome on top. If you're trying to read progress on a terminal from VHR imagery without a site visit, you need to know what to look for besides the outline.
The build sequence, in order
Full containment tanks (the design used on nearly every new LNG import or export terminal) go up in a fairly fixed order, and each stage has a distinct signature from above.
Foundation and base slab. A bare concrete ring or disc, usually with a gap or raised rim at the perimeter where the outer wall will sit. No height, no shadow worth measuring yet. This is the stage where a tank is easiest to miss entirely if you're scanning a busy site.
Outer wall (the containment wall). The prestressed concrete outer wall gets slip-formed or jump-formed in a continuous pour, climbing a few meters a day. In imagery this shows as a ring that's visibly taller each pass, often with a crane or formwork rig riding the top edge. At this stage there's no roof, so you can sometimes see straight down into the structure if the sun angle cooperates, which is the clearest tell that you're looking at an open shell and not a sealed, operating tank.
Inner tank. Once the outer wall is standing, crews start the inner tank, usually 9% nickel steel for the cryogenic barrier, built up inside the concrete ring. The inner shell is shorter than the outer wall and sits inside it, so from directly overhead you may briefly see two concentric circles: the outer wall rim and the inner wall a few meters in from it. That concentric-ring look is one of the most reliable construction-stage markers in LNG tank construction stages imagery, and it disappears once insulation and cladding close the gap.
The dome lift, and why it matters
The roof is where the real tell is. Full containment domes are built flat on the floor, then raised into place with an air-lift (pressurizing the shell with blowers until the dome floats up the inner wall) or, less often, a jacking system. Before the lift, the structure reads as an open cylinder with a flat disc sitting at the bottom, visible from above as a different texture or shade inside the ring. During the lift itself, which usually takes under a day, the dome's shadow and apparent diameter change fast if you happen to catch two passes close together. After the lift, the dome is seated at the top of the outer wall and the vessel starts reading as a closed, domed structure, the shape most people associate with a finished tank.
That's the trap. A tank reads as "done" in a single overhead image the moment the dome lift is complete, but mechanical completion is still months away. Insulation (perlite fill, in most designs), the suspended deck, piping penetrations, and the outer roof membrane all come after the dome is seated, and none of that is visible from above once the roof is closed. A single snapshot after lift-off can make a tank look finished when it still needs a hydrotest, nitrogen purge, and cooldown before it ever holds product.
Reading a tank against the schedule
A single image after the dome lift can't tell you that. Month-over-month sequencing is what actually tells you where a unit sits against the EPC's own schedule: bare slab, climbing wall, concentric rings, flat interior, dome seated, then no further visible change because everything left happens inside a sealed shell. Refinery Progress tracks that sequence across every tank and module on a site monthly, so a lender or trader gets the structure-growth timeline instead of a single ambiguous photo.